The Project Management Unit

Established under Ministry of Construction, Department of Highways


The Technical Assistance Consultant

PADECO


The Contractors / The Project Management and Construction Supervision Consultant

To be determined

About

Project Components 

Over 300km of Road Rehabilitation


The main component is the rehabilitation of national highways (Yangon – Pathein and Bago-Thanlyin highways) and expressway (Yangon-Mandalay expressway km0-km63). On the highways, deteriorated macadam pavement is being widened and upgraded to asphalt concrete. On the expressway, the cement concrete pavement will be overlaid with asphalt concrete, and the shoulders widened.

Pilot maintenance projects


Pilot contracts will be awarded for around 80km of periodic road maintenance using improved techniques, and new models for contracting. The locations of the pilots are to be determined.

Project Stakeholders

The project owner is the Ministry of Construction, Department of Highways

The project is financed by the Asian Development Bank (click here for more information) and the ASEAN Infrastructure Fund.

moc-logo

adb-logo

Status

Construction is planned to begin in 2019. This is after the following steps are completed: a) parliamentary approval of the project, b) signing a loan agreement, c) procurement of contractors and supervision consultant, and d) provision of support to residents affected by or relocated because of the project. Construction work is concentrated during the dry season. During the rainy season heavy equipment cannot move on local roads, but instead granular materials are transported to the site by barge and stockpiled ready for the dry season.

Timeline

12 Dec 2017 Call for expression of interest for supervision consultant

10 Jan 2018 Deadline for submission of EOI for supervision consultant

Feb 2018 Call for tenders of road works packages and supervision consultant

Jul 2018 Planned award of road works packages

Jul 2021 Completion of road works packages